Thursday, January 4, 2007

Load

Provisional Production Schedule

Pre-Production

Week No.

Provisional Dates

Details

Week 1- Week3

11 Dec – 31 Dec

Begin storyboarding, find location, organise crew

Week 4

1 Jan – 7 Jan

Organise cast, finalise storyboard, begin art dept prep

Week 5

8 Jan – 12 Jan

Final shoot prep, rehersals, costumes & styling

Principal Photography

Week No.

Provisional Dates

Details

Week 5

13 Jan – 14 Jan

Principal Photography – 2 days

Week 6

15 Jan – 21 Jan

Contingency photography

Week 7

22 Jan – 28 Jan

Montage scene photography

Post Production

Week No.

Provisional Dates

Details

Week 8

29 Jan – 2 Feb

Video week – solve any problems

Week 9

5 Feb – 11 Feb

Extra photography ( contingency) and sound recording

Week 10 – Week 13

12 Feb – 6 March

(4 weeks)

Picture Edit

Week 14

9 March – 13 March

Grading, show film